For a bathroom renovation, in what order should I do the projects.?

I will be renovating my bathroom soon. I will do new tile around the bathtub, new linoleum, new paint, new fixtures and sink……basically all the bathroom surfaces, with the exception of the bathtub, will be new. I’ve done all these things (tile, linoleum) before and I am comfortable with it, but I’ve never done them all together as one complete project. Do you have any suggestions as to where to start and what order to do these things in. Any other advice would be appreciated as well.

No tags for this post.

One Response to For a bathroom renovation, in what order should I do the projects.?

  1. dragonfire says:

    demo
    replace plumbing valves, check drains
    backing for drywall and tile board
    drywall ( greenboard or newer paperless moisture rated drywall ) tile backboard
    mud and tape drywall
    texture drywall
    prime and paint drywall
    tile bath tub surround
    set vanity cabinet plus vanity top
    set sink and under cabinet plumbing
    set flooring
    set toilet
    set baseboards